NGCP eyes full power transfer capacity within Vis-Min by Q3 

NATIONAL GRID CORP. of the Philippines (NGCP) has committed to fully energizing the Mindanao-Visayas interconnection project (MVIP) by the third quarter of this year.

“NGCP expects to gradually increase the transfer capacity of the facility over the coming months and to reach its full capacity of 450 megawatts (MW) by the third quarter of 2023,” NGCP said in a statement on Wednesday.

Earlier this month, NGCP announced that it had started to energize the MVIP with an initial load of 22.5 MW being transferred from Mindanao to Visayas. The 52-billion transmission project is crucial as it is expected to connect the country’s three main grids, allowing the transfer of power surpluses to regions experiencing deficits.

The Department of Energy has said earlier that it expects a transfer capacity of 450 MW by June to July. The MVIP was certified in 2018 as an Energy Project of National Significance, allowing its speedy approval process. It was initially targeted for completion by December 2020, though it was delayed by the pandemic.

“NGCP clarifies that proper, mindful, and responsible generation and transmission planning are key to a stable grid. Basic principles such as individual island self-sufficiency, decreased inter-island interdependency, and transmission redundancies must be considered,” the grid operator added.

“Development in all sectors involved in the power industry must be coordinated, with due attention given to each,” it added.

For this year, NGCP also expects to complete the Hermosa-San Jose 500-kilovolt (kV) transmission line project as well as the third stage of the Cebu-Negros-Panay backbone project.

The Cebu-Negros-Panay interconnection project consists of a 230-kV backbone, which will supply the rest of the Visayas from Cebu.

Since 2009, NGCP said it had spent P300 billion in upgrading the country’s transmission system.

“But despite NGCP’s best efforts, delays in the completion of certain projects could not be avoided due to the pandemic,” NGCP said.

“Construction works had to be temporarily suspended due to quarantine regulations. Even when restrictions were eased, NGCP could not fully resume work on the projects because of health and safety protocols,” it added.

It also said right-of-ways issues and delays in the delivery of parts and equipment contributed to the delays in its projects.

NGCP has built a total of 3,729 circuit kilometers of transmission lines and 28 substations, and has installed 31,190 megavolt amperes of transformer capacity in the past 14 years. — Ashley Erika O. Jose

Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Get the daily email that makes reading the news actually enjoyable. Stay informed and entertained, for free.
Your information is secure and your privacy is protected. By opting in you agree to receive emails from us. Remember that you can opt-out any time, we hate spam too!

Latest

Economy

By Keisha B. Ta-asan, Reporter INFLATION likely slowed for a fourth straight month in May due to favorable base effects and a decline in...

Economy

By Luisa Maria Jacinta C. Jocson, Reporter THE NATIONAL Government’s (NG) debt service bill more than doubled in March from a year ago, data...

Economy

INVESTMENT APPROVALS by the Board of Investments (BoI) more than doubled as of mid-May, led by renewable energy projects. The Board of Investments (BoI)...

Economy

THE DEPARTMENT of Finance’s (DoF) Privatization and Management Office (PMO) is targeting to dispose of at least 143 properties worth P2.5 billion for the...

Economy

ACEN Corp. has secured approval from the government of New South Wales to increase the capacity of its battery energy storage system in Australia....

Economy

LOPEZ-LED Energy Development Corp. (EDC) is further expanding its geothermal power generation capacity in the Philippines with two prospects scheduled for drilling next year,...

You May Also Like

Investing

Almost 100 jobs are thought to be under threat at smart home energy technology manufacturer myenergi. The Grimsby firm, named one of the UK’s...

Investing

The number of small businesses planning to increase prices to their customers is set to rise dramatically this quarter, further fuelling inflationary pressures. A new quarterly analysis of...

Economy

By Kyle Aristophere T. Atienza, Reporter AROUND eight out of 1,000 Filipinos are “modern slaves,” according to a global index that tracked populations’ vulnerability...

Investing

Canary Wharf Group and The Felix Project, a food redistribution charity have agreed a long-term partnership that will see them join forces to tackle...

Disclaimer: SmartRetirementReport.com, its managers, its employees, and assigns (collectively "The Company") do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

Copyright © 2021 SmartRetirementReport. All Rights Reserved.